One of the job scope done for this project is drilling holes and preparing injection packer staggered along the leaking points, sealing of the leakage at tunnel segment with low-viscosity and injected grout and subsequently patch surface crack points and removal of packer.
Once the injection has solidified , all injection packers are removed, injection holes are sealed, depending on the construction depth. Any unnecessary or unsightly sealing material is removed.
Machinery Used : WIWA 2K-Injekt 14025
Chemical Used : MC-Injekt GL-95 & GL-95TX
: NCL-DH ACRYLIC SEAL (DH-50)
Working at height : Platform Ladder (Caged)
Job done for the tunnel track bed injection is drilling hole and preparing injection packer at 100mm – 300mm spacing staggered along the crack lines, injected grout and subsequently patch surface crack line and removal of packer.